Please publicize the reality of a local housing association apartment in Jung-gu, Ulsan
The local housing association was first established in 2014 and is expected to move in at the end of October this year
For nearly a decade, intermediate payments, interest, and additional surcharges have been incurred, but union members have tried to endure the pain of cutting off blood and flesh to somehow complete the apartment
However, in April, the union leader and the contractor demanded an additional 120 million won for each household in the name of delayed construction due to rising raw material prices and the strike of the construction union of the Ukraine War, and the subsequent increase in loan interest
After that, even though I made it clear that there was no additional contribution, the record was recorded. In September, about a month before the completion of the project, we demanded 106 million won for the additional contribution due to the increase in construction costs
The first apartment sale price is about 450 million won, plus the first additional contribution of 120 million won, the second additional contribution of 160 million won, and the additional registration tax, which will be added after that, is over 700 million won
Can you believe the sale price of 700 million apartments of 34 pyeong in Ulsan, where there is no subway, not in Seoul or the metropolitan area
Since there is no subway in Ulsan, there is no concept of station influence, so the school district has the most impact on apartment prices, but in the case of this apartment, there is no elementary, middle, or high school walkable
It’s ridiculous that an apartment in a rural area with no station or school district costs 700 million
In the case of this apartment, there was a lot of contribution due to the unsold shopping mall because it was a residential and commercial complex, but there are 99 shopping malls in a residential and commercial complex Twenty-six of them were sold and the union members were responsible for all the remaining unsold shopping malls, but I don’t understand that the first construction company in charge of design and construction does not take any responsibility
Even if it’s a 700 million-won apartment, if the materials inside are luxurious and well-built, I’ll try to understand it even if I’m not convinced, but after a recent preliminary inspection, I felt like I lost a ray of hope in a very messy state
All the finishes were messed up, and the boiler walls of the apartment that hadn’t moved in were full of cracks
Even though the construction work is full of defects, the construction company is still unable to cut any additional contributions
If I can turn back time, I want to go back to 10 years ago before I joined the union
Please look at my writing and look at the pictures of the flying construction of this apartment
image text translation
(1)Cracks on the exterior wall outside the windowimage text translation
(2)Bad finish under stair railing
(1)Poor installation direction of shoe cabinet lower gap finish micro hole and poor condition outdoor air chamber hoseimage text translation
(2)Handrail painting contaminated toilet seat horizontal bad
(1)Floor of outdoor air chamber Downward Shelter Floorimage text translation
(2)Reception details
(3)Floor whole edge split
(4)Floor Whole Edge Cracked Outdoor Air Conditioning Shelter
(5)Toilet Biting Occurs Water cannot flow towards the drain
image text translation
image text translation
(1)The floor waterproof paint in the outdoor unit room is poor. It’s all happening soonimage text translation
(2)Damage to the inside of the kitchen sink shelf
(1)Cracks in the wall of the main room veranda. The multi-purpose room wall finish condition is poorimage text translation
(2)Open the door frame of the main room
(1)In entrance shoe cabinet lower finish micro and condition poor kitchen island dining table step poor constructionimage text translation
(2)Poor finish of boiler room wall cracks and hole finish condition poor ceiling wallpaper joint finish condition
(1)The main building is yours to protectimage text translation
(2)The front door doesn’t fit so it doesn’t close well
(3)salary-characteristic
(4)Poor perforation and poor detector power when installing boiler
(1)Missing dressing room detector and poor construction of residential kitchen fire extinguisher installation condition poorimage text translation
(2)ceiling light
(3)wire exposure
(4)Living Room Ceiling Finishing Condition Bad Living Room Ceiling Lighting Wire Exposure
(1)Living room window break. Wall painting defect bubble above veranda faucetimage text translation
(2)Toilet tile contamination and joint construction condition poor door due to gap occur Interference when opening and closing